Automated Coke Drum Switching
and
Safety Interlocks
by Bruce Kerr
Fluor Daniel
Introduction
Why are refiners today installing safety interlocks and even fully automating
the coke drum switch?
Delayed Cokers are very manpower intensive units
that require a great deal of operator attention. Through the years refiners, that have
Delayed Cokers, have seen and/or have read many incident reports where operators have
inadvertently opened valves creating serious safety problems. Results from these incidents
can be and have been devastating, not only to equipment loss and unit downtime but
moreover serious injury to personnel and even death.
Operating Philosophies Differ
Operations personnel differ in as far as operating philosophy throughout the
Delayed Coking industry. One refiner may want a fully automated system, this system would
use the DCS to initiate valve movements for the drum switch. Sequencing programs can be
installed in the DCS to allow for the drum switch from the air free step through the
switch itself without outside operators doing the switch. This system could also have a
complete Safety Interlock in place that would not only prevent catastrophic hot oil losses
to the atmosphere but also prevent operational upsets. Another philosophy may have the
outside operator monitoring valve movements from a safe location, on the switch deck, and
setting steam seals between valve sequencing during the drum switch. Some refiners may
prefer to have a basic interlock system that will prevent erroneous valve movements, which
may cause catastrophic oil losses or blocked process flow to the coker heater. This type
system could be operated by manual valves with proximity switches mounted to the valve or
operated locally from a panel or push button station at either an air, electric, or
hydraulic operated valve with no valve movements initiated from the DCS.
Many refiners are installing this technology in their facilities, whether it be retrofitted to
an existing unit or on a grass roots unit. Installing simplified systems to the fully
automated DCS control scheme and variations stages of automation in-between.
Design Considerations and Installation
There are several issues to consider when deciding to install Coke Drum
Switching Automation and Safety Interlocks. When it comes to safety interlock systems
refiners differ in their philosophy with respect to what type of voting logic to install.
Many refiners use 1 out of 2 voting logic where some refiners use 2 out of 3, the later
being more reliable. The 2 out of 3 voting logic means that losing one switch will not
stop the permissive, but an alarm will let the operator know that there is a switch
malfunction. On the other hand, the 1 out of 2 voting logic, if one switch fails means the
permissive will need to be bypassed to continue the drum switch.
One issue is deciding whether to retrofit existing valves with switches. If these valves are
manual type valves, installing switches external to the valve are not as reliable, due to
the environment the switches are exposed to verses enclosing the switches on a automated
valve. Many refiners install pneumatic and electric actuators to the valves incorporated
in the drum switch. One consideration could be to install hydraulic actuators especially
if the unit has a hydraulic unheading system. These units are very compact and can be
retrofitted to the hydraulic skid for the unheading device.
While trying to decide the magnitude of the automation and interlock system,
consider the type of unit that is being interlocked. A four drum unit verses a two drum
unit will impact that decision. The reason being is a four drum unit has inherently more
risks for operator error than a two drum unit. The four drum unit has two pair of drums
operating and what happens is an operator moves the right valves on the wrong pair of coke
drums.
Many refiners are installing ball valves for isolation around the coke drum.
Some refiners prefer these valves for ease of installation of the safety interlock
switches and automating the coke drum switch. There are some valves that are fitted with
throttling capability for ease of depressuring coke drums and warming of the coke drum
prior to switching. The ball valve makes it easier for this type of operation. This is not
to say that these switches cannot be installed on wedge plug valves, they can. There is a
refiner on the West coast that has a system with all hydraulic operated wedge plug valves
and this system operates well.
How the System Works
Attached is a drawing of a pair of coke drums and piping systems with automated
valves. This drawing can be used, throughout this section, as a reference ( see
attachment 1)

Click for larger image
Once the decision has been made to automate and interlock the drum switch, the
designer needs to follow the existing coke drum switch procedure as close as possible when
building the interlock matrix. The reason for this is to keep changes, to what the
operators have been doing for years, to a minimum. When reading through this procedure,
remember that some valve movements have probably occurred simultaneously. These valves
must be opened and closed in a sequence if they are incorporated into the interlock
system. In an interlock system, certain conditions must be met for an interlocked valve to
be opened or closed.
Most refiners keep a log of near miss reports or
incident reports that have occurred during coke drum switching activities. This is a good
starting point for deciding what type of incidents the interlock will prevent from
occurring and the magnitude of automation and interlock to be installed.
Basically, to build an interlock matrix, one must walk through the coke drum
switch sequence. Starting with the air free of the coke drum, pressure test, warm-up,
switch, steamout, drum cooling, to the coke drum vent and drain. Each valve movement
through the switch sequence should be looked at as far as a "what can happen"
scenario.
Going through the sequence for a typical drum switch starting with air freeing
the coke drum, the first valve to open is the steam to the drum at the utility manifold.
Normally there are no conditions that need to be met to make this valve movement.
The next step would be to pressure test the drum. The coke drum vent valve must
be closed to do this step. If the coke drum has some type of eductor system, for top head
removal, it would be necessary for the interlock to verify that the valve to the eductor
has been closed to prevent pulling a vacuum on the coke drum. Some refiners block the coke
drum safety valve on the discharge when the drum is taken out of service for decoking. If
this is the case then the system needs to verify that this valve is opened to prevent over
pressuring the coke drum during the pressure test and to ensure that the safety is lined
up when the drum is switched into.
The next sequence is the coke drum
warm-up. The warm-up/utility isolation valve and the warm-up valves will be opened along
with the coke drum overhead vapor valves. When the warm-up/utility and warm-up valves are
opened the system needs to verify that the coke drum inlet isolation valve is closed to
ensure isolation from the hot feed, and the utility isolation valve is closed to ensure
isolation from the condensate generated from the warm-up step. To complete the valve
movements for the warm-up step, the coke overhead vapor valves must be opened. The system
needs to verify that the coke drum atmospheric vent valve is closed to prevent the release
of hydrocarbon vapor to the atmosphere. The coke drum blowdown valves can be interlocked
closed at this point to prevent depressuring the fractionator to the blowdown system. This
particular interlock will prevent operational upsets. The blowdown valves are already in
the interlock system for another situation, so the system can act as a monitor of valve
positions associated in the interlock system to prevent not only safety incidents but also
operational upsets.
Prior to switching the coke drum many refiners dryout the steam at the utility
manifold, of the full drum, in anticipation of the switch. Several valve movements occur
with the coke drum switch that are included in the interlock. The first valve is opening
the inlet isolation valve on the empty drum or drum being switched into. The
warm-up/utility isolation valve should be closed. This step ensures isolation of the hot
feed from the warm-up and utility systems. Move the switch valve from the full coke drum
to the empty coke drum. The system verifies that the inlet isolation valve on the empty
drum is open to prevent blockage of process flow through the heater. The system also
verifies that the coke drum overhead vapor valves are open to ensure a pathway and to
prevent the coke drum safeties from lifting. Again the system can act as a watch-dog by
verifying that the warm-up/utility isolation is closed and the coke drum atmospheric vent
valve is closed to prevent the release of hydrocarbons to the atmosphere.
The next step in the sequence is to inject steam into the full coke drum or the drum that was
switched out of. For this step to occur, the utility isolation valve and warm-up utility
isolation valve must be opened. When the utility isolation valve is opened the system
verifies that the warm-up valve is closed to ensure isolation from that system. The
warm-up/utility isolation valve will be opened next to allow steam to enter the full coke
drum. Again the system verifies the warm-up valve is in the closed position. At this point
the system verifies the position of the switch valve making sure that the valve is set
filling the opposite coke drum. The next valve to close is the feed inlet isolation valve
on the drum that has just come off-line or is steaming.
The next step in the sequence is to put the off-line coke drum overhead vapors into
the blowdown system. The valve movements in this sequence is opening the blowdown valves
and closing the overhead vapor valves. At this point one of the blowdown valves can be a
ball valve with throttling capability along with one of the overhead vapor valves.
Installing throttling capability will try and minimize the fractionator upsets when
swinging the overhead vapors from the fractionator to the blowdown system. When the
blowdown valve is opened the system verifies that the feed inlet isolation valve is closed
to ensure the coke drum is off-line. When the overhead vapor valves are closed the system
verifies the position of the switch valve being into the opposite drum or in the
circulation position. This will prevent process flow blockage through the heater.
Once the on-line drum overhead vapors have reached operating temperature then the coke drum
overhead line flushing oil is opened to the on-line drum. The flushing oil is injected to
minimize coking in the coke drum overhead vapor system. The interlock system will again
verify that the overhead vapor valves are open ensuring this drum is on-line and hot
flushing oil is not opened up into an off-line drum.
Once the steaming is complete, water is opened to the drum for cooling. This
step doesnt require an interlock. When drum reaches a satisfactory water level,
usually the top level detector, and overhead temperature and pressure is low enough, the
coke drum vent and drain can be opened. The interlock will verify that the feed inlet
isolation valve is closed to ensure the drum is off-line. Also the system will verify that
the overhead vapor, blowdown, flushing oil, and antifoam injection valves are closed to
prevent a release of hydrocarbons to the atmosphere.
The interlock system can be as complex as what refiners want to make it. Whatever
decision is made and the complexity of the system, this technology exists and refiners are
using it. Refiners must commit to maintaining the system, as is for any new technology or
equipment installed in their plants.
|